Installation Instructions for 100mm and 150mm clips in CONCRETE
February 2, 2026
Follow these steps to correctly install beam clips in concrete:
- Mark holes using beam clip as template
- Drill holes with 13mm drill bit
- Insert bolts and fix to structure and tighten 100kpa
- Set laser or measure for level / measure and cut rod lengths
- Install rod into Beam clip and protrude rod approximately 10mm above bottom of beam clip
- Install top nut and tighten 100kpa until tight and snug to concrete
- Install bottom nut and screw up approximately 100mm above bottom of threaded rod
- Install 45mm retaining nut and adjust to suit level line
- Install bracket over pipe
- Lift pipe to level and slide clip onto 45mm retaining nut until snug fit
- Tighten top nut down onto bracket to 100kpa and snug to top of bracket